Assets Valuation of Gelun Khola Hydropower Project (3.2 MW)

  • Project: Assets Valuation of Gelun Khola Hydropower Project (3.2 MW)
  • Client: Gelun Khola Hydropower Company Pvt. Ltd.
  • Location: Jugal Rural Municipality, Sindhupalchowk District
  • Date: August 2025

This project consists of preparation Asset Valuation Report of Gelun Khola Hydropower Project (3.2 MW) which includes review of available design/documents, PPA documents, generation data and relevant legal documents made available by the Client. The Consultants has completed all the assignments as per ToR.

The major components of the project are headworks arrangement, headrace pipe, forebay, penstock pipe, anchor blocks, saddle supports and surface powerhouse. Headworks comprises of an overflow diversion weir, undersluice, side intake, intake canal including gravel trap and overflow side spillway and settling basin. The power generated from the project is evacuated by 33 kV transmission line built by Baramchi Hydropower Project to NEA substation at Lamosanghu, Sindhupalchowk.

Overall services provided by firm

The scope of services will include, but not be limited to carrying out the following activities:


  • Review of Feasibility Study Report

  • Review of available documents (built up drawings, PPA document, generation data and legal documents)

  • Field Visit and review status of existing structures

  • Preparation of Independent Hydrological Analysis

  • Identify major issues/problems in the project

  • Identify major additional and maintenance works required in the project

  • Review status of exiting EM equipment

  • Project Cost Estimate based on Quantity Estimate and Current Rates

  • Finding project repair, maintenance and additional cost

  • Project valuation based on Actual energy generation

  • Project valuation based on revenue generation

  • Prepare Asset valuation Report of the project

Related Project

Due Diligence Audit for Project Cost Verification of Middle Hongu Khola B Hydropower Project (22.9 MW)

Project: Due Diligence Study of Middle Hongu Khola B Hydroelectric Project (22.9 MW)

Client: Gaurishankar Power Development Ltd.

Date: September 2025

Due Diligence Study of Super Sabha Khola Small Hydropower Project (4.1 MW)

Project: Due Diligence Study of Super Sabha Khola Small Hydropower Project (4.1 MW)

Client: Sankhuwasaba Power Development Pvt. Ltd.

Date: Completed

Due Diligence Study of Super Sabha Khola A Hydropower Project (9.412 MW)

Project: Due Diligence Study of Super Sabha Khola A Hydropower Project (9.412 MW)

Client: Sankhuwasaba Power Development Pvt. Ltd.

Date: Completed

Become a Client

Let's work together for better tomorrow. We help you organize and build your infrastructure projects.

Contact Us

Become our Partner

We have been providing value added services to foreign consulting firms from across the globe who may be interested to establish the business activities in Nepal.

Become Our Partners

Join Our Team

Work with passionate & result oriented people who are expert in their field and makes remarkable impact on what they are doing partnering with clients and community.

Career