This project consists of preparation Asset Valuation Report of Jhyari Khola Small Hydropower Project (2 MW) which includes review of available design drawings/ as built up drawings, PPA documents, generation data and relevant legal documents made available by the Client. The Consultants has completed all the assignments as per ToR.
The major components of the project are headworks arrangement, headrace pipe, forebay, penstock pipe, anchor blocks, saddle supports and surface powerhouse. Headworks comprises of an overflow diversion weir, undersluice, side intake, intake canal including gravel trap and overflow side spillway, power canal and settling basin. The power generated from the project is evacuated by 7 km long 11 kV transmission line to Loop In Loop Out Switching station at Chapdada, Chautara.